One year in, the Titans still on target for finishing their enclosed stadium by February 2027
As of March 2025, the Tennessee Titans’ ambitious project to construct a state-of-the-art enclosed stadium remains on track for its anticipated completion in February 2027. This 1.7-million-square-foot facility, set to replace the aging Nissan Stadium, is poised to redefine Nashville’s skyline and bolster its status as a premier destination for major sporting and entertainment events.
Project Genesis and Vision
The initiative to build a new stadium was driven by the need to provide a modern, versatile venue that aligns with Nashville’s growth trajectory and the evolving demands of sports and entertainment industries. The existing Nissan Stadium, inaugurated in 1999, had begun to show signs of aging, with studies indicating that necessary renovations could approach $1.95 billion over the remaining years of its lease. This prompted stakeholders to explore more sustainable and forward-thinking solutions.
The envisioned stadium is designed to be a fully enclosed, domed structure with a seating capacity ranging between 55,000 and 60,000. It will feature approximately 170 luxury suites and an artificial turf field, ensuring year-round usability irrespective of weather conditions. The design emphasizes a modern aesthetic while incorporating elements that reflect Nashville’s unique cultural heritage, aiming to create a venue that resonates with both locals and visitors.
Financial Framework and Approvals
The project’s financial structure is a collaborative effort between the Titans, the city of Nashville, and the state of Tennessee. The total estimated cost stands at $2.1 billion, with funding apportioned as follows:
- Tennessee Titans: $840 million
- State of Tennessee: $500 million
- Metro Sports Authority Revenue Bonds: $760 million, to be repaid through mechanisms such as a 1% Davidson County hotel occupancy tax, in-stadium sales tax, 50% of sales tax from future development of the stadium’s campus, and ticket taxes and fees.
forbes.com
This funding model was solidified following a decisive 26-11 vote by the Metro Council on April 25, 2023, paving the way for the project’s commencement.
Construction Milestones and Progress
Construction officially broke ground in 2024, marking the beginning of a meticulously planned timeline aimed at ensuring the stadium’s readiness for the 2027 NFL season. Over the past year, significant milestones have been achieved:
-
Foundation and Structural Work: By December 2024, all foundation work was completed, providing a robust base for the stadium’s superstructure. Concurrently, concrete columns across various levels—including Field, Plaza, 100, Suite, Stair Core, and 200 Levels—were erected, establishing the structural framework.
newnissanstadium.com -
Elevated Decks and Concourses: The construction of elevated concrete decks progressed steadily, with multiple levels under development. Notably, the main concourses are designed to offer 360-degree access on all levels, a significant enhancement from the previous stadium layout. These concourses will be wider and equipped with modern amenities, including frictionless markets and nearly double the number of restrooms, aiming to improve the overall fan experience.
newnissanstadium.com -
Precast Seating Bowl: In late January 2025, the installation of the precast stadium bowl commenced. This phase involves setting approximately 2,400 pieces of precast stadia, with an average of 20 pieces being installed daily. This development brings the seating areas to life, ensuring that every seat is padded and positioned closer to the field than in any other NFL stadium, enhancing spectator engagement.
newnissanstadium.com -
Steel Superstructure: The erection of the steel superstructure is slated to begin in early February 2025. This phase will extend from the upper concourse to the roof, marking a significant step toward defining the stadium’s iconic silhouette.
newnissanstadium.com
Workforce and Operational Dynamics
The construction site has witnessed a consistent increase in workforce, reflecting the project’s escalating demands. As of October 2024, approximately 650 workers were on-site, with projections indicating a peak labor force of 1,600. This scaling up ensures that various construction phases proceed concurrently, adhering to the established timeline.
Community Engagement and Sustainability Initiatives
Beyond the physical construction, the project emphasizes community involvement and sustainable practices:
-
Educational Collaborations: Artwork from Metropolitan Nashville Public Schools (MNPS) students adorns the fencing along the east side of the current stadium, fostering a sense of community pride and involvement.
newnissanstadium.com -
Water Conservation Efforts: The stadium design incorporates two large cisterns capable of storing a combined 400,000 gallons of water. This feature underscores the project’s commitment to sustainability by facilitating efficient water reuse.
newnissanstadium.com
Anticipated Impact on Nashville’s Event Hosting Capabilities
The completion of the new stadium is expected to significantly enhance Nashville’s ability to attract and host major events:
-
Super Bowl Aspirations: With the modern amenities and enclosed design of the new stadium, Nashville positions itself as a strong contender to host future Super Bowls, potentially as early as 2029. The city’s track record of successfully organizing large-scale events, coupled with the new stadium’s capabilities, bolsters its bid.
axios.com -
NCAA Final Four and Other Major Events: The versatile design of the stadium makes it suitable for a variety of events, including the NCAA Final Four, concerts, and conventions, thereby diversifying Nashville’s event portfolio and stimulating economic growth.